Tallahassee’s new Southside Transit Center at the corner of Orange Avenue and Meridian Street is finally in the home stretch — but it is running about a year behind. The city originally expected to finish at the end of 2025. Now completion is expected sometime in 2026, after a steel beam frame was installed incorrectly and had to be reworked (WCTV).
That one mistake is a useful reminder for anyone building anything in Tallahassee, from a bus station to a back porch: errors in the structure are the most expensive ones to fix, because everything after them has to wait.

A StarMetro battery-electric bus. Photo: 2019 Proterra XR+ StarMetro by Mr post22, CC BY-SA 4.0, via Wikimedia Commons
What the Southside Transit Center is
The project is a new hub for StarMetro, the city bus system, on Tallahassee’s Southside near Florida A&M University. In 2023 the city received $15 million in federal money from the U.S. Department of Transportation to build it. City staff said the goal was to make transit “more equitable and more accessible,” with new Southside routes so riders walk shorter distances between their stop and their home (WCTV, 2023).
That grant was part of about $36 million for StarMetro, which also included $1 million from the state and $20 million to help convert city buses to electric by 2035 (WCTV, 2023; see also WFSU). That is why the new center includes charging arms for electric buses.
Where construction stands (October 2026)
In its October 2026 update, the city reported (WCTV):
- The primary structural steel and the roof systems are complete.
- Six of the eight bus-charging arms are installed.
- Crews are working on interior framing and finishes, plus mechanical, electrical and plumbing (MEP) systems.
- Exterior finishes were expected to be installed and completed in October.
The city has not given a specific opening date.
Why a steel error causes a long delay
Structural steel sits at the very start of the building sequence. If a frame is set wrong, the roof, walls, framing, electrical, plumbing and finishes can’t move forward until it is corrected — and correcting it usually means new engineering review, new or modified steel pieces, and new inspections. The reports do not say who was responsible for the error, and we are not guessing. But the pattern is common on projects of every size:
- Shop drawings and field work don’t match. Steel is fabricated off-site from detailed drawings; small layout or anchor-bolt errors show up only when pieces arrive.
- Inspections catch it late. A problem found after the next trade has started costs far more to fix.
- Every downstream trade waits. One structural fix can push back roofing, metal framing, electrical and drywall by weeks or months.

StarMetro’s existing bus station on North Duval Street, downtown Tallahassee. Photo: Star Metro Bus Station N Duval St by Michael Rivera, CC BY-SA 3.0, via Wikimedia Commons
Lessons for your own project
You don’t need a $15 million budget to learn from this. If you are building an addition, a garage, a deck or a commercial build-out in Tallahassee:
- Hire licensed pros for structural work. Framing, beams, headers and foundations are not handyman jobs. Here is when you need a licensed contractor instead of a handyman, and how to verify a Florida contractor license.
- Don’t skip the framing inspection. Make sure the structure is inspected and approved before walls are closed with drywall.
- Ask for drawings that match the permit. The plans the city or county approved should be what is built. Changes should be in writing.
- Build schedule buffer into the contract. Agree up front on what happens if work must be redone — who pays and how the schedule changes.
- Keep photos. Photos of the structure before it is covered are cheap insurance if questions come up later.
For contractors: public work is a real opportunity
City, county and federally funded projects like this one hire general contractors, steel erectors, electricians, MEP subs and finish trades. If you want to compete for that work, start with our guide on how to win public construction projects in Tallahassee and Leon County. And make sure GCs can find you: list your business free on Tallahassee Contractors.
Leer en español: versión en español de este artículo.
Sources: WCTV (Oct. 1, 2026); WCTV (June 2023); WFSU (July 2023).